← Back to Portal
SLP Alaska
🔩 SCAFFOLD INSPECTION

Daily Scaffold Inspection

OSHA 1926.451 & 1926.452 Compliant

Basic Information

Foundation & Base

ItemOKDeficientN/A
Base plates/mudsills adequate and secure
Scaffold level and plumb
Adequate base support on firm foundation
Screw jacks properly set and secure

Planking/Decking

ItemOKDeficientN/A
Planking secured and in good condition
Platform fully decked (no gaps)
No damaged, cracked, or weak planks
Proper overlap at supports (min 6")

Guardrails

ItemOKDeficientN/A
Top rail installed (42" ± 3")
Mid rail installed (21" from platform)
Toeboards installed (min 3.5")
Guardrails secure and undamaged

Access

ItemOKDeficientN/A
Proper ladder/stair access provided
Ladder secured to scaffold
Ladder extends 3 ft above platform
Stairs installed properly with handrails

Frame & Structure

ItemOKDeficientN/A
Frames properly connected and secured
Diagonal bracing installed
All pins, clips, and locks secured
No damaged components

Ties & Anchorage

ItemOKDeficientN/A
Scaffold tied to structure
Ties adequate and secure
Tie spacing compliant (26' horizontal, 30' vertical)

Overhead Protection

ItemOKDeficientN/A
Overhead protection required?
Overhead protection adequate if required

Platforms

ItemOKDeficientN/A
Platforms level
Platform width adequate (min 18")
Platforms fully planked

Safety

ItemOKDeficientN/A
Fall protection required (>10 ft)
Fall protection available if required
Tag system in place
Warning signs posted if needed

Load & Use

ItemOKDeficientN/A
Scaffold properly tagged
Load capacity posted
No overloading
Material properly stored on platform

Weather & Environment

ItemOKDeficientN/A
Debris removed from platforms
Ice/snow removed
Weather conditions safe for use

General Condition

ItemOKDeficientN/A
No unauthorized modifications
Scaffold complete and ready for use
Competent person inspected

Additional Items

ItemOKDeficientN/A
Outriggers used if required
Outriggers level and secure
Casters locked (mobile scaffolds)
Scaffold inside power line clearance
Electrical hazards present
Scaffold accessible by public

INSPECTION STATUS: INCOMPLETE

Based on checklist responses

AnthroSafe™ Field Driven Safety|© 2026 SLP Alaska, LLC